Design & Construction Philosophy

As it was the case with the Øresund Fixed Link project, the Fehmarnbelt project is expected to be executed as contracts under which the contractors will carry out the detailed planning, the design and are responsible for the construction works (Design & Construction Philosophy). This will be based on a clear allocation of tasks, responsibilities and risks between Femern A/S and the contractors.

A Design & Construction contract has the following characteristics and project phases:

  • Femern A/S is responsible for preliminary analyses, environmental surveys, geotechnical investigations etc. for use in the plan approval process during which the authorities set out the terms and conditions for the construction process and for the completed project. This may, for instance, relate to requirements regarding noise, dust, water quality, waste handling, access etc.

  • The authorities shall approve the project. In Denmark this will be in the form of a Construction Act while in Germany, the combined road and rail project must be approved by the Schleswig-Holstein plan approval authority. The final alignment and layout of the structure will be decided at this time.

  • Femern A/S’ functional requirements as well as requirements concerning planning and execution will be set out. An illustrative design will be prepared as a specific example of how the task could be executed. This, however, will only be a representation of the final project.

  • The project will be sent out for international tender under current EU regulations. The project will be divided into several contracts. Initially, Femern A/S will invite contractors to prequalify, i.e. prove that they have the qualifications and capacity to execute their respective part of the project. Selected contractors will subsequently be invited to bid. Following receipt of the bids, Femern A/S will evaluate them and the construction contracts will be awarded to the contractors that have submitted the economically most advantageous bids.

  • From the signing of the construction contract the contractor will prepare and present the initial detailed project to Femern A/S. The contractor shall also obtain the specific permissions required for this type of construction project. The construction period will last for approximately six years, a compact process that is likely to involve several thousand people per year at its peak.

  • Towards the end of the construction project, activity will gradually diminish.

  • Up to the inauguration of the link, a number of tests will be carried out, i.e. of the railway, emergency procedures etc. Furthermore, the operational management and monitoring of the link will be established.

  • Prior to the opening, a number of new suppliers and contractors will be appointed relative to the operation and maintenance of the completed link, including manning the toll station, control and monitoring, road service and ongoing maintenance of the link.

As was the case with the Øresund Fixed Link, the Fehmarnbelt Fixed Link will cross national borders. Many aspects related to the production/construction are subject to detailed laws and regulations in more than just one country. Other aspects are prescribed in technical norms and standards. Aspects which are subject to detailed rules are for instance:

  • Permissible extent of noise and dust, e.g. from production sites to avoid disturbing local residents and businesses

  • Working environment and health & safety measures

  • Traffic to and from the production sites – on land as well as at sea

  • Control of sediment spill in the water from excavation works

European technical norms
With respect to technical norms and standards, the extensive development of Eurocodes (EN) means that the way to conduct is more or less harmonized in Denmark and Germany (as in the rest of EU). Certain cross-border operations require the application of similar rules on activities in both countries and in such situation the most stringent legal requirements should be followed.

Femern A/S wishes to act as a good corporate citizen which means that Femern A/S invests considerable resources for making sure that both its organization and the contractors engaged by it are properly aware of the applicable rules. In addition to enhanced awareness, Femern A/S requires that training and control programs are put in place for ensuring proper compliance with the applicable rules.

 

Rødbyhavn as seen from Fehmarnbelt. Photo: Jan Kofoed-Winther.  
Possible production and construction sites

Further information can be found in the reports:

Outline of possible production sites, pdf

Outline of possible construction sites – Puttgarden and Rødbyhavn, pdf

Further reports can be found under Publications 

Caissons for the Øresund Bridge 204 m high pylons. Photo: Øresundsbron.

Impress    |    Privacy Policy    |    Terms of use   |   FAQ   |   Sitemap   |   Links  |  Vacancies

Femern A/S
Vester Søgade 10
DK - 1601 Copenhagen V
T + 45 33 41 63 00
F + 45 33 41 63 01
E info@femern.dk
The Fehmarnbelt Fixed Link
Femern A/S is tasked with designing and planning of a fixed link between Denmark and Germany across the Fehmarnbelt. Femern A/S is a subsidiary of the Danish, state-owned Sund & Bælt Holding A/S, which has experience from the construction of the fixed links across the Great Belt and the Øresund.
Visit our Infocenters
Femern info centre Burg

Ohrtstraße 40
D-23769 Fehmarn | Map

Opening hours:
Tuesday: 3pm to 6pm
Wednesday: 10am to 1pm
Saturday: 10am to 2pm

More info