True
Preparation phase

Important project milestones

The Fehmarnbelt Fixed Link will very likely be built as a 17.6 km long immersed tunnel for combined rail and road traffic. Based on the preliminary investigations and planning, all indicates that an immersed tunnel is the best solution in terms of traffic, safety and environmental factors.

August 2011
In August 2011, Femern A/S prepared a revised construction estimate and timetable for the immersed tunnel. This was carried out as a consequence of the June 2011 decision to locate the tunnel production site at Rødbyhavn.

See Consolidated construction estimate, August 2011

See Revised timetable for the Fehmarnbelt coast-to-coast project, August 2011

 

June 2011
In June 2011, the Danish Parliament's Financial Committee extended the planning budget for the coast-to-coast section of the link, including the ramp and approach areas on land. Budget resources for works that were originally meant to occur only during the construction phase are thereby transferred already to the planning phase. Femern A/S has thus started to prepare tendering for the construction and to plan a Vessel Traffic Service (VTS) system that can monitor shipping during the construction phase.

The planning budget is EUR 376 million, whereas the construction estimate for the entire project from coast to coast including the ramp and approach areas on land accounts for EUR 5.5 billion (both 2008 prices). After 39 years, user fees will have compensated for these investment costs as well as for those into the Danish hinterland infrastructure. The coast-to-coast section of the link itself including the ramp and approach areas on land will be paid off after 33 years.

See Finance Committee’s Legal Document 149, 23 June 2011 (in Danish)

 

June 2011
On 1 June 2011, Danish politicians agreed with Femern A/S’ recommendation, that the production site for the tunnel elements should be located at Rødbyhavn. The Rødbyhavn selection at this early point in the planning is a consequence of a new requirement from the EU. It demands that all crucial parts of the project, including production facilities, must be included as an integrated part in the Environmental Impact Assessment (EIA) report for the entire project.

SeeFemern A/S recommendation to the Minister for Transport on the selection of Rødbyhavn as the production site (in Danish)


February 2011
In February 2011, the Danish politicians behind the project declared an immersed tunnel to be the preferred technical solution. The decision rests on the Femern A/S recommendation from November 2010.

See Femern A/S' recommendation for the preferred technical solution for the EIA process, November 2010

See Note on consolidated construction estimate, November 2010

See Revised timetable for the Fehmarnbelt coast-to-coast project, November 2010


June 2010
In June 2010, the Danish Parliament's Financial Committee extended the planning budget for the coast-to-coast link from EUR 161 million to EUR 254 million. The extension provides for increased costs of approx. EUR 54 million and for carrying out activities earlier as planned in the process for approx. EUR 36 million.

See Finance Committee's Legal Document 140, 3 June 2010  (in Danish)

 

July 2009
On 10 July 2009, the Bundesrat in Germany approved the Act that ratified the state treaty signed with Denmark in September 2008.


June 2009
On 18 June 2009, the Bundestag approved the Act that ratified the state treaty.


March 2009
On 26 March 2009, the Danish Parliament passed the Act on Planning for a fixed link across the Fehmarnbelt and at the same time ratified the state treaty that had been signed with Germany in September 2008.

See Act on the design of a fixed link across the Fehmarnbelt, with associated hinterland infrastructure


September 2008
On 3 September 2008, the Danish and German Ministers for Transport signed a state treaty on establishing a fixed link across the Fehmarnbelt.

See State Treaty


June 2007
On 29 June 2007, the Danish and German Ministers for Transport signed a declaration of intent on establishing a fixed link across the Fehmarnbelt.

 

Impress    |    Privacy Policy    |    Terms of use   |   FAQ   |   Sitemap   |   Links  |  Vacancies

Femern A/S
Vester Søgade 10
DK - 1601 Copenhagen V
T + 45 33 41 63 00
F + 45 33 41 63 01
E info@femern.dk
The Fehmarnbelt Fixed Link
Femern A/S is tasked with designing and planning of a fixed link between Denmark and Germany across the Fehmarnbelt. Femern A/S is a subsidiary of the Danish, state-owned Sund & Bælt Holding A/S, which has experience from the construction of the fixed links across the Great Belt and the Øresund.
Visit our Infocenters
Femern Infocenter Burg

Ohrtstraße 40
D-23769 Fehmarn | Map

Opening hours:
Tuesday: 3pm to 6pm
Wednesday: 10am to 1pm
Saturday: 10am to 2pm

More info