A traditional production method in an excavated casting basin will require a basin of about 220,000 m2, excavated up to a depth of about 10.5 m below sea level. In addition to this, an area of about 300,000 m2 will be required for site facilities, concrete batching plant etc.
A temporary harbour will need to be constructed for the supply of materials and equipment, and adequate access by road will be required. In the event of an industrial production facility being used, the area for the basin can be reduced to about half the size of the basin for a traditional construction method, but the overall area will need to be the same. It is expected that up to 1,000 staff will work at each site at peak production periods.
A dewatering system will ensure dry working conditions in the basins. The excavated soil will be stored temporarily in an area adjacent to the basins and the site facilities, and can be used to return the site to its original state after production of the elements. As an alternative, the basins and site area can be turned into a marina or industrial harbour area.
The production sites must meet all legal and local environmental requirements with regard to noise, dust, vibration, dewatering etc. Main activities such as concrete casting take more than 24 hours and will mean working around the clock. The anticipated requirements for one tunnel element production site with four production lines are as follows:
Figures on the production of tunnel elements (estimates)
| Total length of the link | 21 km | |
| Immersed tunnel length | 19 km | |
| Production site for tunnel elements | ||
| Number of elements | 95 | |
| Length of each element | 200 m | |
| Concrete | 2.500.000 m3 | |
| Reinforcement | 350.000 ton | |
| Production time | 36 months, excluding construction period of prefabrication site | |
| Number of production sites | 2 | |
| Area of each production site | 1000 x 500 m2 | Ideal max. distance from tunnel alignment 120 km |