In November 2010, Femern A/S published two construction estimates based upon conceptual designs, one for a cable-stayed bridge and one for an immersed tunnel. In February 2011, it was decided that the immersed tunnel was the preferred technical solution.
In June 2011, the Danish Parliament gave its approval for the construction estimate of November 2010 of 5.1 billion EUR for the immersed tunnel to be increased by 0.4 billion EUR to 5.5 billion EUR. The increase occurred as a result of a decision to locate the production facilities for the tunnel elements in Rødbyhavn and not in Poland as assumed in the estimate of November 2010.
It is planned that the bill for the Construction Act will be brought before the Danish Parliament during the 2014-2015 parliamentary year, and will include the construction budget for the preferred technical solution.
|
Construction estimate for an immersed tunnel |
June 2011 |
|
|
Construction costs |
3.8 billion EUR |
|
|
Other works |
0.3 billion EUR |
|
|
Total construction costs |
4.1 billion EUR |
|
|
Project management, operational preparations |
0.7 billion EUR |
|
|
Reserves |
0.6 billion EUR |
|
|
Total gross costs |
5.5 billion EUR |
|
View the consolidated construction estimate of August 2011 here.